Committee discusses County purchase of two West Maui water systems for up to $6 million

Mon, Jul 27, 20262 h 07 min
Fact Check with Gemini

The committee discussed buying two private water systems priced at $3.5 million and $2.5 million; the chair said the item was for discussion only. It is expected at Council Member Sugimura's committee on August 4, and the County will not buy without PUC approval.

Key moments

8:22Water department presentation begins
35:30Public testimony: "I'm fully in support"
53:45Question on purchase price versus appraised value
1:01:39"If the PUC doesn't approve it, then we will not buy it"
2:04:10Next steps explained

The meeting, in order

The total price is up to $6 million, not counting closing costs.

The larger system has three wells, two tanks and 402 active connections.

Its price is $3.5 million, and it was appraised at $8,056,000.

The smaller system's price is $2.5 million, and it was appraised at $1.987 million.

The water department said the sellers would run the systems for about six months during the handover.

A testifier said 77% of West Maui water systems are owned by private entities.

Another testifier supported the purchase but questioned paying above the appraised value for one system.

The County would buy the companies' assets, not the companies themselves.

The department said the County will not buy the systems if the PUC does not approve the sale.

An official said only PUC approval is needed for the purchase itself.

The chair said the item was for discussion only.

The item is expected at Council Member Sugimura's committee on August 4.

If the council acts in August, closing could come around April next year.

What happens next

The administration plans to answer follow-up questions from committee staff, ideally by the August 4 meeting. After committee approval, the item would go to the full council for final approval. Once the council approves, the County would start the PUC process. Staff were asked to note a request to clarify when approval from a state water agency is needed.