Central Maui wastewater reclamation facility funding

Last meeting Oct 19 4 meetings 14 updates 1 meeting in the past 30 days

Water and Infrastructure CommitteeBudget, Finance, and Economic Development CommitteeMaui County CouncilBill 30 (2026)
Fact Check with Gemini

On Oct. 19, 2026, the environmental management director said the Central Maui wastewater plant is projected to start in late 2029 or later, but should be running before the school needs service in July 2031. The 14.9-acre site is under 15 acres, so it does not need the Land Use Commission. The county holds environmental permits and is working through land approvals.

Sources checked Nov 9, 2026.

What was said, in order

  1. The director confirmed the 14.9-acre plant site does not need the Land Use Commission because it is under 15 acres.

    Said at a meetingOpen on YouTubeOpen this meeting
  2. The director said the county has environmental permits for the new plant and is working through land approvals.

    Said at a meetingOpen on YouTubeOpen this meeting
  3. The environmental management director said the new plant should be running before the school needs service in July 2031.

    Said at a meetingOpen on YouTubeOpen this meeting
  4. The new Central Maui wastewater plant is projected to begin operating in late 2029 or later.

    Said at a meetingOpen on YouTubeOpen this meeting
  5. The committee recommended the bill on first reading with nine ayes.

    Said at a meetingOpen on YouTubeOpen this meeting
  6. The wastewater project needs 7.13 percent of the parcel, or 14.9 of its 209 acres.

    Said at a meetingOpen on YouTubeOpen this meeting
  7. The open space fund is limited to land conservation, so it must be repaid for the part of the parcel used for wastewater.

    Said at a meetingOpen on YouTubeOpen this meeting
  8. The parcel was first bought with open space money for about $5.2 million.

    Said at a meetingOpen on YouTubeOpen this meeting
  9. The committee backed moving $372,933 from the Sewer Fund to the open space fund for land needed for the Central Maui Wastewater Facility.

    Said at a meetingOpen on YouTubeOpen this meeting
  10. The member withdrew the loan motion for now.

    Said at a meetingOpen on YouTubeOpen this meeting
  11. The member said the project is stalled while waiting on the County plant, and the community needs its affordable housing and school.

    Said at a meetingOpen on YouTubeOpen this meeting
  12. A member said the Central Maui wastewater facility may not be working until 2031.

    Said at a meetingOpen on YouTubeOpen this meeting
  13. A member proposed a $500,000 zero-interest loan to design a private wastewater plant for part of a country town development.

    Said at a meetingOpen on YouTubeOpen this meeting
  14. Bill 30 adds $3.5 million for the Central Maui Regional Wastewater Reclamation Facility in Waikapū.

    Said at a meetingOpen on YouTubeOpen this meeting