Līloa Drive extension in Kīhei
Last meeting Sep 14 2 meetings 22 updates
Disaster Recovery, International Affairs, and Planning CommitteeWater and Infrastructure CommitteeThe department said on September 14, 2026 that the first phase of the Līloa Drive extension is expected to begin in 2027. The project would extend the road about 8,600 feet and had a $34 million cost estimate in 2023, with federal aid and a bond request expected to cover the rest. In 2023 the committee deferred the item, and testifiers urged planning the road together with housing and a high school.
Sources checked Nov 14, 2026.
What was said, in order
The department said the first phase of the Līloa Drive extension is expected to begin in 2027.
Deferral of the road extension project presentation item: The committee deferred the road extension item with no objections.
The department said it is evaluating roundabouts at every intersection.
A council member asked whether the road's route still fits if the county builds housing beside it.
The department said it will consult with DOT on where bus stops should go.
The department said the rest would likely come from federal aid and a bond request.
The vice chair said the road project is connected to housing.
Closing oral testimony: The chair closed oral testimony on the item.
The testifier asked that the design include places for bus stops.
The testifier asked for a master plan covering the road, housing and a high school together.
A testifier said about 100 acres of county land along the road could be available for housing.
One testifier supported the project and called it long overdue.
The current construction cost estimate is $34 million.
The plan is to advertise the project for construction in December 2024.
The team expects to finish its environmental assessment, a study of the project's effects, in spring 2024.
If three power transmission poles must be moved, the team will likely need to go to the Public Utilities Commission.
The team plans to hold three to four community outreach meetings.
The team is studying two main bridge designs for a stream crossing.
The extended road would have two 11-foot travel lanes with wide shoulders for bikes.
The project would extend the road about 8,600 feet.
Designation of two resource persons under Rule 18: Two project team members were designated as resource persons (people who can answer the committee's questions) with no objections.
The department will send early consultation letters as it begins public review of the environmental assessment.